Assmang, Cato Ridge

About This Project

  • Upgrade of control systemFurnace 4/5
  • Furnace 5 control system implementation and PLC equipment supply – AMCR 268 C 3 Part E
  • Control system design and Supply of Software
  • Furnace 4 Control System Upgrade & Implementation
  • Furnace 1&2 – Control Desk Upgrade
  • Furnace 6 – Control System Upgrade & Implementation
  • Furnace 5 – Furnace Quantum CPU Upgrade
  • CRA – Control System Upgrade Preliminary Design
  • Furnace 4 – Constrol System Upgrade – Old Gasplant Control and Design
  • Furnace 4 – Control System Upgrade – Implementation on the Clay Gun System
  • Furnace 4 – Control System Upgrade – PLC & SCADA
  • Furnace 3 – Control System Upgrade – Implementation of the Clay Gun System
  • Furnace 3 – Control System Upgrade – Instrumentation & Control System
  • Furnace 5/6, 3/4 & CRA Control Room Interior Design
  • Furnace 3 – Control System Upgrade_Instrumentation & Control System – Scope of work
  • Control Room Upgrade – STB Panel and I/O on Fire System and Additional Hardware
  • Control Room Upgrade Relocate Furnace 1&2 Control Room
Category